Bailey Road completion timeline

Sachse

Summary

The last change order on the 2021 bond-funded Bailey Road rebuild adds nearly $494,000 for water lines, drainage, concrete and cleanup — but it's paid from West Creek Lane project savings, not new money. The $11.6 million project should be substantially complete by June 26.

At a glance

Total mentions
3
Last 30 days
0

Last discussed Jun 15, 2026.