Blackburn/Ingram Road four-lane vs. two-lane
The most contentious road project: a four-lane widening estimated at $38 million that requires buying 19 houses (option 1) or 11 houses plus rebuilding screening walls (option 2), versus roughly $20 million to simply rebuild the existing two-lane road without adding capacity. Committee members flagged recently built homes in the take line and questioned whether widening a short stretch is worth the cost.
Neighborhood streets package
A resident begged the council to put the Cornwall/Sachse Estates area streets — deteriorating since 2022 — into the 2027 bond, and questioned why the published bond list didn't include them.
West Creek Lane and Woodbridge Parkway reconstruction
Staff proposed a $12.2 million full rebuild of Woodbridge Parkway, but PACER pavement scores show most of the road rated 1 or 2 (good condition). Committee members pushed back hard, leaning instead toward folding a smaller repair amount into the neighborhood streets package.
Industrial Drive reconstruction design
The badly failing industrial park road will be rebuilt, but the two design options split the council: the standard design removes on-street parking businesses use, while the business-friendly option violates the city's design manual and costs about $200,000 more. Direction moved toward the standard design, with debate about whether industrial areas deserve their own standards.
Williford Road reconstruction contract
Council awarded the $6.1 million construction contract to rebuild Williford Road. One resident asked when the road will actually be finished, since the contract's schedule wasn't stated.
Pedestrian safety study for The Station
A new traffic study found 87 crashes over three years — including a fatality — and recommended lower speed limits, new all-way stops, and better crosswalks in The Station. The Council acted on the speed limits and is funding the rest through the regular budget. Residents who live there said the changes may mean they no longer feel they need to move.
Merritt Road project timeline
The 1.5-mile Merritt Road project has its right-of-way, archaeology, and plans done, but waits on FEMA, the Corps of Engineers, and utility relocations. Construction bids are expected in fall 2026, and the final cost won't be known until bids come in.